This is the current projects biweekly update for the week of November 5th, 2018. As of 11-06-2018 Park Place Property Group has 6 projects under construction: 1306 W Hood Ave, 5809 N Washtenaw Ave, 1837 N Mozart St, 4581 N McVicker Ave, 1531 W Granville Ave, and 1050 N Taylor Ave.

All 6 projects are at different stages of construction, please check in biweekly for updates, next update will be Tuesday, November 20th.

On to the update:

5809 N WASHTENAW AVE

Construction Update: Since our last update we’ve received notification from the City of Chicago that inspections will be done soon. Meanwhile, we’ve been working on the exterior of the home. The siding is going up, windows are being installed, roof is finished, back porch is done as well as the mud room in the back. Next is finishing up the siding, soffits, gutters, windows, window cappings, etc. Once the inspections are done we will move into closing up the walls and doing drywall.

PICTURES
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave
20181106-5809 N Washtenaw Ave

1837 N MOZART ST

Construction Update: Since our last update all of the reamining framing has been finished and the basement dugout has begun. The foundation wasn’t as deep as we needed it to be, that means we have to underpin the foundation if we want to go lower which we do. Aside from that, the flat roof has been finished and we’re upgrading the water service to accomodate the number of beds and baths that are in the building. The permits have been received for that and we’re ready to go, the guys will be getting started on that next.

PICTURES
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St
20181106-1837 N Mozart St

1306 W HOOD AVE

Construction Update: Since our last update a lot has happened, the stucco has been painted, the front porch has been demo’d, and the windows have all been isntalled. Aside from that, the entire house is now drywalled and it is looking amazing! There’s a bit of mudding and sanding left on the top floor but you can really see how beautiful this home is going to be. We’re leaving some of the original wood work which I’m excited about because it’s in really good condition, the ceiling in the dining room is stunning!

PICTURES
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave
20181106-1306 W Hood Ave

4581 N MCVICKER AVE

Construction Update: The architectural plans have been submitted to the City of Chicago so we should be receiving permits soon, I’d say in about 2-3 weeks from now. Below are the architectural plans and the elevations of what the house will look like when it’s done.

20180830-IMG_1780
FLOOR PLANS
4581 N McVicker Arch Drawings - Basement
4581 N McVicker Arch Drawings - First Floor
4581 N McVicker Arch Drawings - Second Floor
ELEVATIONS
4581 N McVicker Arch Drawings - Elevations 1
4581 N McVicker Arch Drawings - Elevations 2

1531 W GRANVILLE AVE

Construction Update: The architectural plans are done and have been submitted to the City of Chicago, now we just wait to get them back and begin construction. Below is the architectural plans of what the house will look like when it’s done.

20180906-IMG_1838
FLOOR PLANS
1531 W Grangille Arch Drawings - Basement
1531 W Grangille Arch Drawings - First Floor
1531 W Grangille Arch Drawings - Second Floor

1050 N TAYLOR AVE

Construction Update: The architectural plans are done and have been submitted to the Village of Oak Park, now we just wait to get them back and begin construction. Below is the architectural plans of what the house will look like when it’s done.

20180824-IMG_1745
FLOOR PLANS
1050 N Taylor Ave Arch Drawings - Basement
1050 N Taylor Ave Arch Drawings - First Floor
1050 N Taylor Ave Arch Drawings - Second Floor

– – –

That’s it for our biweekly update! Just a friendly reminder, we have now switched to posting updates twice a month or biweekly. If you are a partner of ours you will be able to see more sizable updates since a lot more can happen in two weeks time. Please stay tuned, next update will be Tuesday, November 20th.

Let us know if you have any questions or thoughts in the comments below, we would love to hear from you!

Until next time!